Detailed Engineering design and Bid Document preparation of Choir-Sainshand-Zamiin-Uud Road
Client: Ministry of Road, Transport and Tourism, Government of Mongolia
Services: Detailed Engineering Design and Bid documents preparation
Period: From Sep 2004 – May 2005
Associated with: MCPC Mongolia (JV)
KFW spot Improvement of Selected road sections
Client: Ministry of Road, Transport and Tourism, Government of Mongolia
Services: Detailed Engineering Design and Bid documents preparation
Period: From Jul 2005 to Feb 2006
Associated with: MCPC Mongolia (JV)
Detailed Engineering of Selected Road Sections in Ulaanbaatar
Client: Department of Roads, Municipality of Ulaanbaatar
Services: Preparation of Detailed Engineering Design and Technical Specifications
Period: From Dec 2006 to Mar 2007
Detailed Design and Project Management Consulting Services for Second Ulaanbaatar Services Improvement Project
Client: Project Management Unit on behalf of Municipality of Ulaanbaatar
Services: Preparation of detailed designs, technical specifications, bill of quantities and engineering cost estimates
Period: From Dec 2004 to Jun 2006
Associated with: ICT Pvt Ltd, India and Khot Services, Mongolia
Detailed Engineering design of Ikh Tenger bridge
Client: Ministry of Road, Transport and Tourism, Government of Mongolia
Services: Preparation of drawings, technical specification, bid documents in accordance with the international
standards
Period: From Apr 2007 to May 2007
Associated with: “GBET” Co. Ltd, Mongolia
Detailed Engineering Design for Iron Ore mining – Burgastai Border post
Client: Altain Khuder Co.Ltd
Services: Preparation of Detailed Engineering Design, Technical
Specification and Bid Documents for 168.3 km road between Iron Ore mining – Burgastai Border post in Mongolia
Period: From May 2008 to Nov 2008
Detailed Engineering design for Unt-Murun road
Client: Ministry of Road, Transport and Tourism, Government of Mongolia
Services: Preparation of Detailed Engineering Design, Technical Specification and Bid Documents for 259 km road
Period: From Jan 2008 to Aug 2008
Associated with ICT Pvt Ltd
Detailed Engineering – Gobi-Altai-Kharganii hudag
Client: Department of Roads, Government of Mongolia
Services: Preparation of Detailed Engineering Design, Technical Specification and Bill of Quantities for 87.3 km road
Period: From Oct 2009 to Dec 2009
Project Management and Construction Supervision of Ukhaa Khudag – Gashuun Sukhait Road, Umnugovi Province, Mongolia
Client: Energy Resources LLC, Gobi Road LLC, Mongolia
Services: Project Management and Construction Supervision of 240 km Ukhaa Khudag – Gashuun Sukhait Road, Umnugovi Province, Mongolia
Period: 9 months from the commencement date of services
Construction of Choir-Sainshand -Zamiin Uud road
Client: Department of Roads, Government of Mongolia
Services: Construction Supervision of roads from Choir to Zamiin Uud and access roads to Orgon and Erdene soums
Period: from August 2006 and in progress
Associated with: MCPC Co.Ltd
Construction of Erdenet-Bulgan-Unt road
Client: Department of Roads, Government of Mongolia
Services: Construction Supervision of roads from Erdenet to Unt brigade of Bulgan province
Period: from Apr 2004 and in progress
Associated with: ICT Pvt Ltd, India
Open Programme of Rehabilitation and Spot Improvements of Regional Transport Infrastructure in Selected Provinces of Mongolia (Darkhan, Selenge, Zavkhan)
Client: Department of Roads, Government of Mongolia
Services: Construction Supervision of Selected roads in Darkhan-Uul, Selenge and Zavkhan provinces
Period: from Jun 2006 and Oct 2009
Associated with: MCPC Co.Ltd
Construction of Ulaanbaatar- Darkhan- Altanbulag
Client: Department of Roads, Government of Mongolia
Services: Construction Supervision of 312 km road from Ulaanbaatar to Altanbulag and replacement of 2 existing timber bridges with pre-stressed concrete bridges on Darkhan-Erdenet road
Period: from Jun 1997 and Jun 2000
Associated with: ICT Pvt Ltd, India